Howdy!
Thank you, Oscar! It works quite well. However, I also want to change the process & activity after (or before?) it moves to the other application. I'm trying various combinations, but I can't seem to get the order down properly. What would you suggest?:
MOVE TO OTHER DB:
DWFUtilSetApplication
DWFJobInitiate
REROUTE TO NEW ACTIVITY
DWFBinderReRoute
DWFBinderAddDocument (needed?)
I don't really need any code, but perhaps a bit of guidance on the proper order and if there's anything missing.
Thanks, in advance!
Steve in NYC
"If the automobile had followed the same development cycle as the computer, a Rolls-Royce would today cost $100, get a million miles per gallon, and explode once a year, killing everyone inside."