Calculating working days between two dates

  • Category: Server Side JavaScript
  • Platform: Windows
  • Release: 8.5.3
  • Role: Administrator,Developer,End User
  • Tags: Calculating working days between two dates
  • Replies: 2

Dear All,

Let me know how to find working days between two days after excluding weekends and holidays in xpages.

Please help.

Dec 21, 2014, 1:09 PM
110 Posts
Evaluate the @BusinessDays

var startdate = "@Date(2014;12;1)";

var enddate = "@Date(2014;12;31)";
var weekends = "1:7"; //assuming your weekend is Saturday and Sunday
var holidays = "@Date(2014;12;24):@Date(2014;12;25)"; // assuming your holiday is 24th and 25th December
var formula = "@BusinessDays(" + startdate + ";" + enddate + ";" + weekends + ";" + holidays + ")";
return session.evaluate(formula);

Dec 22, 2014, 3:53 AM
51 Posts
@BusinessDays

Thank you, it is working.